    (1)     This section applies to plans accompanying an application for a demolition order to demolish a building.

    (2)     The plans must—

        (a)     be drawn in accordance with AS 1100, unless the plans were drawn before the standard commenced; and

Note     The standard may be purchased at www.standards.org.au

.

        (b)     show any area covered by the plans that is marked as an easement in the land titles register or on a deposited plan; and

        (c)     if the demolition will require the disconnection of a pipe to the sewerage system—show any point of disconnection of the pipe to the sewerage system; and

        (d)     if the demolition will require the disconnection of a pipe to a water main—show any point of disconnection of the pipe to the water main; and

        (e)     if the demolition will require the disconnection of a pipe to a stormwater drain—show any point of disconnection of the pipe to the stormwater system; and

        (f)     if the demolition will, when finished, alter the surface stormwater drainage on the parcel of land where the work is to be done—show the proposed surface stormwater drainage on the parcel at the completion of the work; and

        (g)     for the parcel of land where the demolition is to be done—include a site plan on a scale of not less than 1:200 showing—

              (i)     the block and section number of the land (or for land under a land sublease, the sublease plan number); and

              (ii)     the boundaries and dimensions of the land.