AUSTRALIAN JOBS ACT 2013 - SECT 22A

Project proponent must notify estimated completion date for a new relevant facility

  (1)   If:

  (a)   the project proponent for a major project gives a draft AIP plan for the project to the Authority; and

  (b)   the project involves establishing a new relevant facility; and

  (c)   the establishment of the facility has not been completed;

the project proponent must:

  (d)   notify the Authority of the estimated date of completion of the establishment of the facility; and

  (e)   do so at or about the same time as the draft AIP plan is given to the Authority.

  (2)   A notification under subsection   (1) must be in a form approved, in writing, by the Authority.