OFFSHORE PETROLEUM AND GREENHOUSE GAS STORAGE (RESOURCE MANAGEMENT AND ADMINISTRATION) REGULATIONS 2011 - REG 4.12

Objection to requirement to vary field development plan

  (1)   If the Titles Administrator gives a petroleum production licensee a notice under regulation   4.11, the licensee may give an objection, in writing, to the Titles Administrator:

  (a)   stating one or more of the following:

  (i)   that the variation should not occur;

  (ii)   that the variation should be in terms different from the proposed terms;

  (iii)   that the varied field development plan should take effect on a date later than the proposed date;

  (iv)   that the date by which the licensee must submit a variation of the plan should be later than the proposed date; and

  (b)   giving reasons for the objection.

  (2)   The licensee must make the objection within:

  (a)   21 days after receiving the notice; or

  (b)   if the Titles Administrator, in writing, allows a longer period--that period.