Diving project plan to be approved

  (1)   This regulation applies if there is an operator for a diving project.

  (2)   The diving contractor must prepare a diving project plan for each diving project in consultation with the operator for the project.

  (3)   The diving project plan must be approved by the operator for the project before diving can commence on the project.

  (4)   The operator must not approve the diving project plan unless the operator is satisfied that:

  (a)   the plan complies with regulation   4.16; and

  (b)   there was effective consultation in the preparation of the plan, as required by regulation   4.18.