(1) NOPSEMA must keep a register of each DSMS and revised DSMS it receives, in a form that allows public access.
(2) The register must record as many of the following details as apply to the DSMS:
(a) the name of the diving contractor;
(b) the date of acceptance;
(c) any conditions on acceptance;
(d) the date of rejection;
(e) the date that acceptance was withdrawn;
(f) the date of any revision notice under regulation 4.11.
(3) NOPSEMA must also record on the register, the following details for each diving project plan it receives under regulation 4.13:
(a) the name of the diving contractor;
(b) the diving project to which the diving project plan applies;
(c) the proposed commencement date of the project;
(d) the date of receipt of the plan.