(1) A titleholder may apply to the Regulator for acceptance by the Regulator of a well operations management plan.
(2) The titleholder must give the plan to the Regulator:
(a) at least 30 days before the proposed start of the well activity; or
(b) if the Regulator allows, and notifies in writing, another period -- within that period.
(3) The plan:
(a) must be in writing; and
(b) may apply to well activities for more than one well; and
(c) may be submitted, with the approval of the Regulator notified in writing, in parts for particular stages of the activity.