(1) If the Regulator believes it may be necessary to withdraw its acceptance of a well operations management plan, the Regulator must, at least 30 days before the Regulator would withdraw its acceptance:
(a) notify the titleholder in writing that the Regulator is considering the withdrawal of the acceptance; and
(b) include in the notification:
(i) an explanation of the reasons why the Regulator is considering withdrawing the acceptance; and
(ii) a date by which the titleholder may give the Regulator any information that the Regulator may take into account before deciding whether to withdraw the acceptance; and
(iii) any other information that the Regulator considers appropriate.
(2) The Regulator may give a copy of the notice to a person other than the titleholder if:
(a) the Regulator considers it appropriate; and
(b) the titleholder agrees in writing.