- (1)
- For subsection 150YR (1) of the PSL Act, this regulation sets out
when safety investigation levy is due and payable.
- (2)
- If an inspection
continues for 3 months or less, safety investigation levy is payable when the
inspection is taken to be complete for subregulation 9 (3).
- (3)
- If an inspection continues for more than 3 months, safety investigation
levy is payable in instalments:
- (a)
- at the end of each period of 3 months,
starting when the inspection starts, during which the inspection continues;
and
- (b)
- when the inspection is taken to be complete for subregulation 9 (3).
- (4)
- The Safety Authority must notify the operator:
- (a)
- within 14 days after
the inspection is taken to be complete for subregulation 9 (3); and
- (b)
- if the inspection continues for more than 3 months within 14
days after the end of each 3 month period;
of the amount of levy, or the amount of an instalment of levy, that is
payable.
Note
The amount of safety investigation levy takes into account the
post-threshold incremental cost of an inspection.
- (5)
- However, if the
Safety Authority fails to notify the operator in accordance with subregulation
(4), the validity of any subsequent notification is not affected by the
failure.
- (6)
- For subsection 150YR (1) of the PSL Act, safety investigation levy is
due 30 days after the Safety Authority notifies the operator under
subregulation (4).