DESIGN AND BUILDING PRACTITIONERS ACT 2020 - SECT 20
Variations after building work commences
20 Variations after building work commences
(1) A building practitioner who does building work must take all reasonable
steps to ensure that, if the building work (other than in relation to a
building element or performance solution) is varied after commencement of the
work from a regulated design for the work, the variation is recorded in the
form and manner prescribed by the regulations for the purposes of this
section. : Maximum penalty--3,000 penalty units (in the case of a body
corporate) or 1,000 penalty units (in any other case).
(2) A
building practitioner who does building work must take all reasonable steps to
ensure that, if the building work (in relation to a building element or
performance solution) is to be varied from a regulated design for the
building element or performance solution, before the varied building work
commences-- (a) a design with the variation is prepared by a registered design
practitioner, and
(b) the registered design practitioner is given (or
otherwise has access to in the manner prescribed by the regulations) any of
the following that are relevant to the provision, by the registered design
practitioner, of a design compliance declaration for the varied design-- (i)
regulated designs,
(ii) design compliance declarations,
(iii)
principal compliance declarations, and
(c) a design compliance declaration is
obtained for the varied design from a registered design practitioner whose
registration authorises the practitioner to provide a declaration as to the
matters to which the declaration relates, and
(d) if a principal design
practitioner has been appointed in relation to the building work, a
principal compliance declaration is obtained that includes the varied design.
: Maximum penalty--3,000 penalty units (in the case of a body corporate) or
1,000 penalty units (in any other case).
(3) A building practitioner who does
building work must take all reasonable steps to ensure that, if the work is to
be varied so as to require a new building element or performance solution for
which a regulated design is required, before the varied building work
commences-- (a) a design for the building element or performance solution is
prepared by a registered design practitioner, and
(b) the registered design
practitioner is given (or otherwise has access to in the manner prescribed by
the regulations) any of the following that are relevant to the provision, by
the registered design practitioner, of a design compliance declaration for the
design-- (i) regulated designs,
(ii) design compliance declarations,
(iii)
principal compliance declarations, and
(c) a design compliance declaration is
obtained for the design from a registered design practitioner whose
registration authorises the practitioner to provide a declaration as to the
matters to which the declaration relates, and
(d) if a principal design
practitioner has been appointed in relation to the building work, a
principal compliance declaration is obtained that includes the design.
:
Maximum penalty--3,000 penalty units (in the case of a body corporate) or
1,000 penalty units (in any other case).