ENVIRONMENTAL PLANNING AND ASSESSMENT ACT 1979 - SECT 4.55

Modification of consents--generally

4.55 Modification of consents--generally

(cf previous s 96)

(1) Modifications involving minor error, misdescription or miscalculation A consent authority may, on application being made by the applicant or any other person entitled to act on a consent granted by the consent authority and subject to and in accordance with the regulations, modify a development consent granted by it to correct a minor error, misdescription or miscalculation. Subsections (1A), (2), (3), (5) and (6) and Part 8 do not apply to such a modification.
Note : Section 380AA of the Mining Act 1992 provides that an application for modification of development consent to mine for coal can only be made by or with the consent of the holder of an authority under that Act in respect of coal and the land concerned.
(1A) Modifications involving minimal environmental impact A consent authority may, on application being made by the applicant or any other person entitled to act on a consent granted by the consent authority and subject to and in accordance with the regulations, modify the consent if--
(a) it is satisfied that the proposed modification is of minimal environmental impact, and
(b) it is satisfied that the development to which the consent as modified relates is substantially the same development as the development for which the consent was originally granted and before that consent as originally granted was modified (if at all), and
(c) it has notified the application in accordance with--
(i) the regulations, if the regulations so require, or
(ii) a development control plan, if the consent authority is a council that has made a development control plan that requires the notification or advertising of applications for modification of a development consent, and
(d) it has considered any submissions made concerning the proposed modification within any period prescribed by the regulations or provided by the development control plan, as the case may be.
Subsections (1), (2) and (5) do not apply to such a modification.
(2) Other modifications A consent authority may, on application being made by the applicant or any other person entitled to act on a consent granted by the consent authority and subject to and in accordance with the regulations, modify the consent if--
(a) it is satisfied that the development to which the consent as modified relates is substantially the same development as the development for which consent was originally granted and before that consent as originally granted was modified (if at all), and
(b) it has consulted with the relevant Minister, public authority or approval body (within the meaning of Division 4.8) in respect of a condition imposed as a requirement of a concurrence to the consent or in accordance with the general terms of an approval proposed to be granted by the approval body and that Minister, authority or body has not, within 21 days after being consulted, objected to the modification of that consent, and
(c) it has notified the application in accordance with--
(i) the regulations, if the regulations so require, or
(ii) a development control plan, if the consent authority is a council that has made a development control plan that requires the notification or advertising of applications for modification of a development consent, and
(d) it has considered any submissions made concerning the proposed modification within the period prescribed by the regulations or provided by the development control plan, as the case may be.
Subsections (1) and (1A) do not apply to such a modification.
(3) In determining an application for modification of a consent under this section, the consent authority must take into consideration such of the matters referred to in section 4.15(1) as are of relevance to the development the subject of the application. The consent authority must also take into consideration the reasons given by the consent authority for the grant of the consent that is sought to be modified.
(4) The modification of a development consent in accordance with this section is taken not to be the granting of development consent under this Part, but a reference in this or any other Act to a development consent includes a reference to a development consent as so modified.
(6) Deemed refusals The regulations may make provision for or with respect to the following--
(a) the period after which a consent authority, that has not determined an application under this section, is taken to have determined the application by refusing consent,
(b) the effect of any such deemed determination on the power of a consent authority to determine any such application,
(c) the effect of a subsequent determination on the power of a consent authority on any appeal sought under this Act.
(8) Modifications by the Court The provisions of this section extend, subject to the regulations, to enable the Court to modify a consent granted by it but, in the extension of those provisions, the functions imposed on a consent authority under subsection (1A)(c) or subsection (2)(b) and (c) are to be exercised by the relevant consent authority and not the Court.