(1) An application for a consent under this Division to construct a pipeline is to be lodged in writing with the Minister.
(2) An application may relate to all or some of the activities for designing and constructing the pipeline.
(3) The application is to include the following information:
(a) the name of the applicant;
(b) an address of the applicant for communications on matters relating to the pipeline;
(c) a facsimile number, or electronic mail address, within Australia for the applicant.
(4) The application is to be accompanied by:
(a) those parts of the pipeline management plan in force for the pipeline that provide for the activities to which the application relates; and
(b) a validation of the proposal to carry out those activities.