(1) An electricity entity may seek an order from a Court under this section if a person erects a building or structure in proximity to a powerline in contravention of section 91 .
(2) The order may be obtained:
(a) on application to a Court that finds the person guilty of an offence against section 91 (4); or
(b) by action in a Court of competent jurisdiction.
(3) The Court may make one or more of the following orders:
(a) an order requiring the person to take specified action to remove or modify the building or structure within a specified period;
(b) an order for compensation from the person for loss or damage caused by the contravention;
(c) an order for costs reasonably incurred by the electricity entity in relocating the powerline or carrying out other work to rectify the contravention.