Queensland Consolidated Acts

[Index] [Table] [Search] [Search this Act] [Notes] [Noteup] [Previous] [Next] [Download] [Help]

BUILDING INDUSTRY FAIRNESS (SECURITY OF PAYMENT) ACT 2017 - SECT 77

Consequences of failing to give payment schedule

77 Consequences of failing to give payment schedule

(1) This section applies if a respondent given a payment claim does not respond to the claim by giving the claimant a payment schedule as required under section 76 .
(2) The respondent is liable to pay the amount claimed under the payment claim to the claimant on the due date for the progress payment to which the payment claim relates.



AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback