BUILDING INDUSTRY FAIRNESS (SECURITY OF PAYMENT) ACT 2017 - SECT 77
Consequences of failing to give payment schedule
77 Consequences of failing to give payment schedule
(1) This section applies if a respondent given a payment claim does not
respond to the claim by giving the claimant a payment schedule as required
under section 76 .
(2) The respondent is liable to pay the amount claimed
under the payment claim to the claimant on the due date for the progress
payment to which the payment claim relates.