ENVIRONMENTAL PROTECTION ACT 1994 - SECT 59A
Lapsing of EIS assessment report
59A Lapsing of EIS assessment report
(1) An EIS assessment report for a project lapses— (a) on the day that is 3
years after the day the chief executive gives the proponent the EIS assessment
report under section 57 (2) ; or
(b) if, before the day mentioned in
paragraph (a) , the chief executive extends the period mentioned in that
paragraph—on the day the extended period ends.
(2) However, if the
proponent applies for an environmental authority before the EIS assessment
report lapses under subsection (1) , the report does not lapse until— (a) if
the application for the environmental authority is refused—the application
is decided and any appeal against the decision is finalised or withdrawn; or
(b) if the application for the environmental authority is granted—the
authority takes effect.