54 Failure to decide application

(1) If the authority fails to decide the mortgageeā€™s application for an exemption certificate by the required day, the authority is taken to have decided to refuse the application.
(2) The
"required day" is the day that is 20 business days after the end of the show cause period for the show cause notice the authority gave the farmer under section 50 .
(3) If the application is taken to be refused under this section, the mortgagee is entitled to be given an information notice for the decision by the authority.