GREENHOUSE GAS STORAGE ACT 2009 - SECT 53

General requirements

53 General requirements

(1) The proposed program must provide for all of the following—
(a) an overview of the activities proposed to be carried out under the proposed GHG permit during all of its term;
(b) for each year of the program period—
(i) the extent and nature of GHG storage exploration proposed to be carried out during the year; and
(ii) generally where the activities are proposed to be carried out; and
(iii) the estimated cost of the activities;
(c) maps that show where the activities are proposed to be carried out;
(d) the composition of GHG streams proposed to be injected under the GHG permit;
(e) a description of any pipeline land for the GHG permit;
(f) reasons why the program is considered appropriate;
(g) another matter prescribed under a regulation.
(2) The proposed program may include any other information relevant to the work program criteria.
(3) The composition of GHG streams to be injected under the proposed GHG permit must comply with section 83 .
(4) A regulation may impose requirements about the form of the work program.
(5) In this section—

"year" , of the program period, means—
(a) the period starting on the day the program period starts and ending on the first anniversary of that day; and
(b) each subsequent period of 12 months or less during the program period starting on each anniversary of that day and ending on—
(i) the next anniversary of that day; or
(ii) if the program period ends before the next anniversary—the day the program period ends.