Relief from procedural requirements
61 Relief from procedural requirements
(1) The tribunal may, by order— (a) extend a time limit fixed for the start
of a proceeding by this Act or an enabling Act; or
(b) extend or shorten a
time limit fixed by this Act, an enabling Act or the rules; or
(c) waive
compliance with another procedural requirement under this Act, an enabling Act
or the rules.
(2) An extension or waiver may be given under subsection (1)
even if the time for complying with the relevant requirement has passed.
(3)
The tribunal can not extend or shorten a time limit or waive compliance with
another procedural requirement if to do so would cause prejudice or detriment,
not able to be remedied by an appropriate order for costs or damages, to a
party or potential party to a proceeding.
(4) The tribunal may act under
subsection (1) on the application of a party or potential party to the
proceeding or on its own initiative.
(5) The tribunal’s power to act under
subsection (1) is exercisable only by— (a) the tribunal as constituted for
the proceeding; or
(b) a legally qualified member, an adjudicator or the
principal registrar.