ENERGY (RENEWABLE TRANSFORMATION AND JOBS) REGULATION 2024 - REG 9

Eligible priority transmission investments—Act, s 20

9 Eligible priority transmission investments—Act, s 20

For section 20 (1) of the Act , each of the following projects identified in the infrastructure blueprint as part of the optimal infrastructure pathway is prescribed as an eligible priority transmission investment—

(a) the project called ‘Stage 1: Borumba connection’ described in the infrastructure blueprint, page 40, as in effect on the commencement;
(b) the project called ‘Stage 2: Central Queensland connection’ described in the infrastructure blueprint, page 40, as in effect on the commencement;
(c) the project called ‘Stage 3: Pioneer-Burdekin PHES and NQ connection’ described in the infrastructure blueprint, page 40, as in effect on the commencement;
(d) the project called ‘Stage 4: Townsville to Hughenden connection’ described in the infrastructure blueprint, page 41, as in effect on the commencement;
(e) the project known as the ‘Gladstone project’ comprised of works for achieving the purposes of the investment for the Central QREZ region described in the infrastructure blueprint, page 29, as in effect on the commencement, other than the second circuit upgrade to enable further REZ capacity in the Banana Range.