Amendment or cancellation of HML declaration on request by relevant road manager
18 Amendment or cancellation of HML declaration on request by relevant road
manager
(1) This section applies if a relevant road manager for an HML declaration is
satisfied the use of HML heavy vehicles under the higher mass limits in an
area or on a route to which the declaration applies (and in or on which a road
for which the relevant road manager is a road manager is situated)— (a) has
caused, or is likely to cause, damage to road infrastructure; or
(b) has had,
or is likely to have, an adverse effect on the community arising from noise,
emissions or traffic congestion or from other matters stated in the approved
guidelines; or
(c) has posed, or is likely to pose, a significant risk to
public safety arising from heavy vehicle use that is incompatible with road
infrastructure or traffic conditions.
(2) The road manager may ask the
Regulator to— (a) amend the declaration to— (i) change the area or route
to which it applies; or
(ii) amend the intelligent access conditions applying
to HML heavy vehicles used under the higher mass limits in an area or on a
route to which the declaration applies; or
(b) cancel the declaration.
(3)
The Regulator must comply with the request.
(4) However, if consent to the
grant of the declaration was given by a road authority under section 163 of
the Law as applied under section 14 — (a) the Regulator may refer the
request to the road authority; and
(b) if the road authority gives the
Regulator its written approval of the request, the Regulator must comply with
the request; and
(c) if the road authority does not give written approval of
the road manager's request within 28 days after the referral is made, the
Regulator— (i) must not comply with the request; and
(ii) must notify the
road manager that the road authority has not given its written approval of the
request and, as a result, the Regulator must not comply with it.
(5) The
Regulator must publish a public notice of the amendment or cancellation.
(6)
The amendment or cancellation takes effect— (a) 28 days after the
Commonwealth Gazette notice is published under subsection (5) ; or
(b) if a
later time is stated in the Commonwealth Gazette notice, at the later time.