Meaning of structure

290 Meaning of structure

(1) In this chapter,
"structure" has the same meaning as it has in the Act .
Examples—
• a roadway or pathway
• a ship or submarine
• foundations, earth retention works and other earthworks, including river works and sea defence works
• formwork, falsework or any other structure designed or used to provide support, access or containment during construction work
• an airfield
• a dock, harbour, channel, bridge, viaduct, lagoon or dam
• a sewer or sewerage or drainage works
(2) This chapter does not apply to plant unless—
(a) the plant is—
(i) a ship or submarine; or
(ii) a pipe or pipeline; or
(iii) an underground tank; or
(iv) designed or used to provide support, access or containment during work in connection with construction work; or
(b) work on the plant relates to work that is carried out in connection with construction work; or
(c) the plant is fixed plant on which outage work or overhaul work that involves or may involve work being carried out by 5 or more persons conducting businesses or undertakings at any point in time.
Note—
This chapter does not apply to the manufacture of plant, see section 289 (3) (a) .