(1) This section applies if the angle measured under section 315F (2) (b) is 75º or more.
(2) This section does not apply to—(a) demolition work; or(b) work erecting or dismantling formwork on or for a structure.
(3) The principal contractor must ensure that at least 1 of the following control measures is used before construction work starts—(a) a gantry is erected along the proposed line adjacent to the sides of each part of the structure from which an object could fall;(b) the adjoining area is closed under section 315M at least to the extent necessary to prevent objects falling on or otherwise hitting persons;(c) a catch platform with perimeter containment screening complying with section 315I is installed—(i) along the sides of each part of the structure from which an object could fall; and(ii) not more than 1m below—(A) if the structure has storeys—the storey of the structure from which an object could fall; or(B) if the structure does not have storeys—the surface from which an object could fall.Penalty—Maximum penalty—60 penalty units.
(4) In this section—
"formwork" includes a structure installed to support formwork.