It is a condition of the major hazard facility licence that the operator of the major hazard facility must pay the relevant fee—
(a) if a major hazard facility licence is granted—(i) within 14 days after receiving notice of the regulator’s decision to grant the major hazard facility licence; andNote—The regulator must notify the operator within 14 days after deciding to grant a major hazard facility licence, see section 580 (5) .(ii) on or before the day in each year that is the anniversary of the day on which the licence was first granted, for the period the licence is granted; or
(b) if a major hazard facility licence is renewed—(i) within 14 days after receiving notice of the regulator’s decision to renew the major hazard facility licence; andNote—The regulator must notify the operator within 14 days after deciding to renew the operator’s major hazard facility licence, see sections 580 (5) and 598 (b) .(ii) on or before the day in each year that is the anniversary of the day on which the licence was renewed, for the period the licence is renewed.