(1) This section applies if a proposed geothermal lease is for a significant project.
(2) The Minister must not grant the geothermal lease until the Minister has been given the coordinator-general's report for the project.
(3) Any coordinator-general's conditions for the geothermal lease must be stated in the lease.
(4) Any other condition of the geothermal lease stated under section 82 can not be inconsistent with the coordinator-general's conditions.
(5) If a mandatory condition for geothermal leases conflicts with any of the coordinator-general's conditions, the mandatory condition prevails to the extent of the inconsistency.
(6) In this section--
coordinator-general's conditions, for the proposed geothermal lease, means the conditions for the lease stated in the coordinator-general's report for the significant project.
coordinator-general's report means the coordinator-general's report under the State Development and Public Works Organisation Act 1971 for the EIS for the significant project.