(1) This part applies if--
(a) equipment or improvements are taken, constructed or placed on land in the area of a GHG authority; and
(b) the equipment or improvements were taken, constructed or placed on the land for use for an authorised activity for the GHG authority; and
(c) the GHG authority continues in force.
(2) However, this part--
(a) does not apply for a GHG stream pipeline; and
(b) is subject to part 15.
Notes--
1 For pipelines, see sections 250 (General provision about ownership while tenure or licence is in force for pipeline) and 252 (Obligation to decommission pipelines on cessation or reduction of tenure).
2 Part 15 (Enforcement of end of authority and area reduction obligations).
(3) In this section--
equipment includes machinery and plant.
improvements--
(a) does not include a GHG well; but
(b) does include any works constructed in connection with a GHG well