Sections 75 and 76--
omit, insert--
'(1) Despite section 74, the mining registrar may refer an application for the grant of a mining claim to the tribunal for hearing.
'(2) The tribunal must fix a date for the hearing and immediately give written notice of the date to each of the following--
(a) the mining registrar;
(b) the applicant;
(c) the EPA administering authority.
'(3) The date must be at least 20 business days after the later of the following--
(a) the last objection day for the application;
(b) the day a section 65 conference about the application ends.
'(1) This section applies if the mining registrar is not satisfied an owner of a reserve consented to an application for a mining claim over the reserve.
'(2) The mining registrar must, within 5 business days after the later of the following, refer the issue of consent to the tribunal for its consideration--
(a) the last objection day for the application;
(b) the day a section 65 conference about the application ends.
'(3) The tribunal must fix a date for the hearing and immediately give written notice of the date to each of the following--
(a) the mining registrar;
(b) the applicant;
(c) the EPA administering authority;
(d) the owner of the reserve.
'(4) The date must be at least 20 business days after the later of the following--
(a) the last objection day for the application;
(b) the day a section 65 conference about the application ends.'.