54C—Conditions requiring approval of certain works and processes
(1) The Authority may,
by conditions of an environmental authorisation, require the holder of the
environmental authorisation to seek the Authority's approval in relation
to—
(a) the
construction or alteration of a building or structure, or the installation or
alteration of plant or equipment, for use for an activity carried on under the
environmental authorisation; or
(b) a
change in a process undertaken under the environmental authorisation.
(2) If conditions of
an environmental authorisation (whether imposed before or after the
commencement of this section) require the holder of the
environmental authorisation to seek the Authority's approval in relation to a
matter of a kind referred to in subsection (1)(a) or (b), an application
for such approval must—
(a) be
made in a manner and form determined by the Authority; and
(b) be
accompanied by the prescribed fee.
(3) If the Authority
requires further information to determine the application, the Authority may,
by notice in writing served on the applicant no later than 2 months after the
application is made, require the applicant to furnish further specified
information in writing.
(4) If further
information is required in respect of an application, the application is to be
taken not to have been duly made until the information is furnished as
required by the Authority.