Schedule 2—Description and map of statutory easements
Width (m) |
Start Point |
End Point | |
---|---|---|---|
Mainline (1) |
18 12 ↑ 6 1 |
Middle of the insulating joint at the outlet of Moomba Meter Station, situate
within section 717, Out of Hundreds (Strzelecki). (M1) |
Survey marker above the pipeline situate on the north-western boundary of
allotment 1 (DP 25326) 2 , Hundred of Munno Para, being south of the Gawler
River. (M2) |
Mainline (2) |
15 10 ↑ 5 |
Survey marker above the pipeline situate on the north-western boundary of
allotment 1 (DP 25326), Hundred of Munno Para, being south of the Gawler
River. (M2) |
Survey marker above the pipeline situate on the south-eastern boundary of part
section 3069 and the north-western boundary of Whites Road, suburb of Bolivar,
Hundred of Port Adelaide. (M3) |
Mainline (3) |
18 12 ↑ 6 |
Survey marker above the pipeline situate on the south-eastern boundary of part
section 3069 and the north-western boundary of Whites Road, suburb of Bolivar,
Hundred of Port Adelaide. (M3) |
Centre line of Mainline Valve No. 30 at the inlet to Torrens Island Meter
Station, situate within section 453, Hundred of Port Adelaide. (M4) |
Taperoo Lateral |
15 7.5 ↑ 7.5 |
Tee on Mainline where the lateral to Taperoo branches off, situate within
section 453, Hundred of Port Adelaide. (T1) |
Centre line of 80 NB blow-off valve at the inlet to Taperoo Meter Station,
situate within allotment 101 (FP 32808) 3 , Hundred of Port Adelaide. (T2) |
Wasleys Loop (1) |
25 16 ↑ 9 |
Face of flange at the upstream end of the isolating valve to the scraper
launcher at the outlet of Wasleys Pressure Reduction Station, situate within
allotment 2, (DP 15928), Hundred of Grace. (L1) |
Survey marker above the pipeline on the southern boundary of allotment 2 (DP
19550) and the northern boundary of Stanton Rd, suburb of Virginia, Hundred of
Munno Para, being south of the Gawler River. (L2) |
Wasleys Loop (2) |
15 10 ↑ 5 |
Survey marker above the pipeline on the southern boundary of allotment 2 (DP
19550) and the northern boundary of Stanton Rd, suburb of Virginia, Hundred of
Munno Para, being south of the Gawler River. (L2) |
Survey marker above the pipeline, situate on the western boundary of allotment
4 (FP 40178), Hundred of Port Adelaide, being on the east side of Bolivar
Channel near St Kilda. (L3) |
Wasleys Loop (3) |
25 16 ↑ 9 |
Survey marker above the pipeline, situate on the western boundary of allotment
4 (FP 40178), Hundred of Port Adelaide, being on the east side of Bolivar
Channel near St Kilda. (L3) |
Centre line of Mainline Valve No. 31L at the inlet to Torrens Island Meter
Station situate within section 453, Hundred of Port Adelaide. (L4) |
Pt Pirie Lateral |
15 5 ↑ 10 |
Tee on Mainline where the lateral to Pt Pirie branches off situate within
section 278, Hundred of Whyte. (P1) |
Face of 80 NB flange at the inlet to Pt Pirie Meter Station, situate within
closed road A (RP 7019) 4 - CT 4089/955, Hundred of Pirie. (P2) |
Whyalla Lateral |
25 17 ↑ 8 |
Centre line of blow-off valve at the outlet of Bungama Pressure Reduction
Station, situate within allotment 3 (DP 24997), Hundred of Pirie. (W1) |
Face of flange at the downstream end of the scraper receiver isolating valve
at the inlet to Whyalla Meter Station situate within allotment 6 (FP 15068),
Hundreds of Cultana and Randell. (W2) |
Pt Bonython Lateral |
25 8 ↑ 17 |
Tee on Whyalla Lateral where the lateral to Pt Bonython branches off, situate
within section 253, Hundred of Cultana. (Y1) |
Centreline of the isolating valve at the inlet to Pt Bonython Meter Station,
situate within section 239, Hundred of Cultana. (Y2) |
Burra Lateral |
15 7.5 ↑ 7.5 |
Tee on Mainline where the lateral to Burra branches off, situate within the
road west of section 588, Hundred of Hanson. (B1) |
Face of 50 NB flange at the inlet to Burra Meter Station, situate within
allotment 2 (FP 1258), Hundred of Kooringa. (B2) |
Peterborough Lateral |
3 1.5 ↑ 1.5 |
Face of 80 NB flange at the outlet of Peterborough Meter Station, situate
within allotment 11 (FP 34199), Hundred of Yongala. (E1) |
Centre line of the isolating valve at the inlet to the Peterborough Power
Station, situate within Kitchener Street, Peterborough township, adjacent to
allotment 88 (DP 1050) Hundred of Yongala. (E2) |
Mintaro Lateral |
20 5 ↑ 15 |
Tee on Mainline where the lateral to Mintaro branches off, within allotment 3
(DP 12055) Hundred of Stanley. (O1) |
Centre line of the isolating valve at the inlet to the Mintaro Meter Station,
situate within allotment 3 (DP 12055), Hundred of Stanley. (O2) |
Angaston Lateral (1) |
15 4.5 ↑ 10.5 |
Tee on Mainline where the lateral to Angaston branches off in Wasleys Pressure
Reduction Station, situate within allotment 2 (DP 15928), Hundred of Grace.
(A1) |
Survey marker above the pipeline situate on the north-western boundary of
allotment 3 (DP 26607) and the south-eastern boundary of Seppeltsfield Road,
Hundred of Nuriootpa. (A2) |
Angaston Lateral (2) |
12 3 ↑ 9 |
Survey marker above the pipeline situate on the north-western boundary of
allotment 3 (DP 26607) and the south-eastern boundary of Seppeltsfield Road,
Hundred of Nuriootpa. (A2) |
Centreline of mainline valve at the inlet to Angaston Meter Station, situate
within part section 67 (CT 3740/14), Hundred of Moorooroo. (A3) |
Nuriootpa Lateral |
5 3.5 ↑ 1.5 |
Face of 80 NB insulating flange at the outlet of the Nuriootpa Meter Station,
situate within section 71, Hundred of Moorooroo. (N1) |
Upstream face of the insulating flange adjacent to Nuriootpa township
isolating valve, situate within the road adjoining section 136, Hundred of
Moorooroo. (N2) |
Tarac Lateral |
3 1.5 ↑ 1.5 |
Tee on Nuriootpa Lateral where the lateral to Tarac branches off, situate
within the road adjoining section 136, Hundred of Moorooroo. (R1) |
Face of insulating flange at the inlet to Tarac Meter Station, situate within
section 136, Hundred of Moorooroo. (R2) |
Dry Creek Lateral |
3 0.9 ↑ 2.1 |
Centre line of 300 NB underground valve at the outlet of Dry Creek Meter
Station, situate within section 482, Hundred of Port Adelaide. (C1) |
Downstream end of underground isolating valve in Dry Creek Power Station,
situate within allotment 16 (FP 9554), Hundred of Port Adelaide. (C2) |
Safries Lateral |
20 10 ↑ 10 |
Tee on Snuggery Lateral where the lateral to Safries branches off, situate
within section 163, Hundred of Monbulla. (F1) |
Face of flange at the downstream end of the isolating valve at the inlet to
Safries Meter Station, situate within section 423, Hundred of Penola. (F2) |
Snuggery Lateral |
20 8 ↑ 12 |
Face of insulating flange at the outlet of Katnook processing plant, situate
within section 336, Hundred of Monbulla. (S1) |
Face of flange at the downstream end of isolating valve of scraper receiver at
inlet to Kimberly Clark Australia Meter Station, situate within allotment 50,
(DP 31712), Hundred of Hindmarsh. (S2) |
Mt Gambier Lateral (1) |
20 12 ↑ 8 |
Tee on Snuggery Lateral at Glencoe Junction where the lateral to Mt Gambier
branches off situate within allotment 11 (DP 31711), Hundred of Young. (G1) |
Face of flange at the downstream end of the isolating valve of the scraper
receiver at the inlet to Mt Gambier Meter Station, situate within allotment 1
(DP 31778), Hundred of Blanche. (G2) |
Mt Gambier Lateral (2) |
20 12 ↑ 8 |
Downstream end of tee at the outlet of Mt Gambier Meter Station, situate
within allotment 1 (DP 31778), Hundred of Blanche. (G3) |
Centre of the insulating joint where the responsibility for the gas transfers
to the Customer, situate within section 685, Hundred of Blanche and being
north of Pinehall Avenue. (G4) |
Notes—
1 The arrow represents the normal direction of
flow of the gas as of the date of the legislation. The figures indicate the
width of the Statutory Easement on each side of the centreline of the pipeline
looking in the direction of the flow.
2 DP denotes deposited plan in the Lands Titles
Registration Office.
3 FP denotes filed plan in the Lands Titles
Registration Office.
4 RP denotes road plan in the Lands Titles
Registration Office.