34—Energy productivity shortfalls
(1) For the purposes
of section 94B of the Act, a "relevant electricity retailer is a retailer
who is subject to the application of this Part (including on account of
regulation 26(5) or 27(4)).
(2) For the purposes
of section 94B(13)(a) of the Act, the requirements imposed under this
Part on a retailer—
(a) to
undertake energy productivity activities under regulation 26 sufficient
to achieve the relevant EPT; and
(b) to
undertake energy productivity activities under regulation 27 sufficient
to achieve any relevant primary subtarget or secondary subtarget,
constitute the activities relating to energy productivity in which a
relevant electricity retailer must engage, and for the purposes of that
section the retailer must engage in those activities to the extent necessary
to achieve compliance with regulation 26(2) or 27(2) (as the case
requires).
(3) For the purposes
of section 94B(13)(b) of the Act, the extent of an energy productivity
shortfall with respect to a particular year—
(a) will
be determined in relation to each of the activities referred to in
subregulation (2)(a) and (b); and
(i)
in relation to energy productivity activities under
regulation 26—an amount equal to the energy productivity shortfall
applying to the retailer for that year;
(ii)
in relation to energy productivity activities under
regulation 27 relating to a primary subtarget or secondary
subtarget—an amount equal to the energy productivity shortfall for the
primary subtarget or secondary subtarget (as the case requires) applying to
the retailer for that year.
(4) For the purposes
of section 94B(2)(a) of the Act, the prescribed base penalty is
$10 000 for each category of shortfall identified under
subregulation (3).
(5) For the purposes
of subsection (2)(b) of section 94B of the Act, the amount payable
under that subsection will be—
(a) in
the case of an energy productivity shortfall under
subregulation (3)(b)(i)—the amount constituting the energy
productivity shortfall (expressed in normalised gigajoules) multiplied
by $21.45; or
(b) in
the case of an energy productivity shortfall under
subregulation (3)(b)(ii)—the amount constituting the energy
productivity shortfall for the relevant primary subtarget or secondary
subtarget (expressed in normalised gigajoules) multiplied by $21.45.