229—Record of standards or engineering principles used
(1) If the design of
plant is required to be registered under Chapter 5 Part 3, the
designer of the plant must record any published technical standard, including
any part of a published technical standard, that was used to design the plant.
Maximum penalty:
(a) In
the case of an individual—$1 250.
(b) In
the case of a body corporate—$6 000.
Expiation fee:
(a) In
the case of an individual—$144.
(b) In
the case of a body corporate—$720.
(2) If the designer of
the plant has not used published technical standards to design the plant, the
designer must record any engineering principles used to design the plant.
Maximum penalty:
(a) In
the case of an individual—$1 250.
(b) In
the case of a body corporate—$6 000.
Expiation fee:
(a) In
the case of an individual—$144.
(b) In
the case of a body corporate—$720.