301—Safe work method statement—copy to be given to principal
contractor
A person conducting a business or undertaking that includes carrying out high
risk construction work in connection with a construction project must, before
the high risk construction work commences, ensure that a copy of the safe work
method statement for the work is given to the principal contractor.
Maximum penalty:
(a) In
the case of an individual—$3 600.
(b) In
the case of a body corporate—$18 000.
Expiation fee:
(a) In
the case of an individual—$432
(b) In
the case of a body corporate—$2 160.