5—Variation of Schedule 4—Complying development
(1) Schedule 4, Part 1—after clause 4 insert:
5—Temporary accommodation in area affected by bushfire
The construction or placement of a building or structure on land on which a dwelling, or part of a dwelling, has been destroyed or significantly damaged by a bushfire if—
(a) the building or structure is to be used as accommodation by the owner of the land; and
(b) the building or structure is a minimum of 20 metres from any remaining or regenerating cluster of vegetation (whether that vegetation is on the land or on adjoining land); and
(c) the owner of the land complies with any requirements of the South Australian Country Fire Service relating to the maintenance of a clearance area between the temporary accommodation and any remaining or regenerating cluster of vegetation; and
(d) the building or structure is to be used as accommodation—
(i) until 1 January 2022; or
(ii) until a Class 1a building on the land is able to be occupied in accordance with regulation 83A,
whichever occurs first.
(2) Schedule 4, Part 2—after clause 17 insert:
18 The construction or placement of a building or structure on land on which a dwelling, or part of a dwelling, has been destroyed or significantly damaged by a bushfire if—
(a) the building or structure is to be used as accommodation by the owner of the land; and
(b) the building or structure is a minimum of 20 metres from any remaining or regenerating cluster of vegetation (whether that vegetation is on the land or on adjoining land); and
(c) the owner of the land complies with any requirements of the South Australian Country Fire Service relating to the maintenance of a clearance area between the temporary accommodation and any remaining or regenerating cluster of vegetation; and
(d) the building or structure is to be used as accommodation—
(i) until 1 January 2022; or
(ii) until a Class 1a building on the land is able to be occupied in accordance with regulation 83A,
whichever occurs first; and
(e) the building or structure complies with the following requirements:
(i) the requirements in—
(A) the relevant clauses of Part 2.1 of the Housing Provisions of the National Construction Code; and
(B) clause P2.2.2 of the Housing Provisions of the National Construction Code; and
(C) clause P2.4.3 of the Housing Provisions of the National Construction Code;
(ii) —
(A) if the site is connected to mains water—the land on which the building or structure is constructed or placed has a 2 000 litre dedicated fire fighting water supply with a tap; or
(B) if the site is not connected to mains water—the land on which the building or structure is constructed or placed has a 5 000 litre dedicated fire fighting water supply with a tap;
(iii) waste water is disposed of through, or connected to, an approved wastewater system, SA Water sewer or council community wastewater system;
(iv) all smoke alarms required under clause P2.3.2 of the Housing Provisions of the National Construction Code are installed and tested;
(v) the building or structure is fitted with a fire extinguisher.