BUILDING ACT 2016 (NO. 25 OF 2016) - SECT 152

Certificate of final inspection (building)
(1)  A building surveyor may issue a certificate of final inspection (building) in respect of permit building work if –
(a) the building surveyor has –
(i) inspected the permit building work under section 149 on completion of the final notification stage for the work; and
(ii) received a standard of work certificate (permit building work) in respect of the work; and
(b) the building surveyor is satisfied that –
(i) the permit building work is completed; and
(ii) the permit building work is in compliance with this Act and the National Construction Code, in so far as it is reasonably practicable to inspect.
(2)  If a building surveyor issues a certificate of final inspection (building), the building surveyor is to –
(a) issue the certificate of final inspection (building) to the owner of the premises where the permit building work was performed; and
(b) provide a copy of it to the permit authority and the licensed builder specified in the relevant permit for the permit building work.