(1) If a tank forming part of a storage system is replaced, an
infrastructure owner of the storage system must ensure that, before the
storage system is used, the storage system incorporates the mandatory
equipment, designed and installed in accordance with the requirements of AS
4897. Penalty: Fine not exceeding 100 penalty units.
(2) Subregulation (1) applies to a storage system whether or not AS 4897 requires all or part of the mandatory equipment (a) to be installed as part of the storage system; and
(b) if so installed, to be installed in accordance with the requirements of AS 4897.
(3) An infrastructure owner of a storage system must ensure that an area
of land that is excavated to enable the replacement of the storage system or
of a fill point, or piping, in the storage system is scrutinised for
contamination by petroleum. Penalty: Fine not exceeding 100 penalty
units.
(4) If scrutiny under subregulation (3) of an area of land
excavated for the purposes of that subregulation detects apparent
contamination of an area of land by petroleum from a storage system, an
infrastructure owner of the storage system must (a) within 7 days
after the apparent contamination is detected, notify the Director, in the
approved form, of the apparent contamination and that an environmental site
assessment in accordance with regulation 26 will be carried out; and
(b)
ensure that (i) an environmental site assessment in accordance
with regulation 26 begins within 14 days after the contamination is
detected; and
(ii) the environmental site assessment is completed in
accordance with regulation 26 ; and
(c) ensure that a report in relation
to the environmental site assessment is completed in accordance with
regulation 26 .
Penalty: Fine not exceeding 100 penalty units.
(5) If a storage system or piping in a storage system is replaced, an
infrastructure owner of the storage system must, before the storage system is
used, ensure that (a) an equipment integrity test is conducted
after all replacement work, including concreting and sealing, is completed;
and
(b) the storage system or piping has passed the test.
Penalty: Fine not exceeding 100 penalty units.
(6) If a tank forming part of a storage system, or piping in a storage
system, is repaired, an infrastructure owner of the storage system must ensure
that before the storage system is used (a) the repair work meets
the requirements set out in AS 4897 as a minimum; and
(b) an equipment
integrity test is conducted on the tank or piping after all repair work,
including concreting and sealing, is completed; and
(c) the repaired tank or
piping has passed the equipment integrity test.
Penalty: Fine not