BUILDING ACT 1993 - SECT 37G

Extension of time to comply with direction

    (1)     A builder who is subject to a written direction to fix building work may ask the relevant building surveyor or authorised person to extend the period for compliance with the direction.

    (2)     A request under subsection (1) must be made before the end of the specified period for compliance with the direction.

    (3)     On a request under subsection (1), the relevant building surveyor or authorised person may grant an extension of the period for compliance with the direction to fix building work if the relevant building surveyor or authorised person considers it appropriate to do so in the circumstances.

    (4)     The relevant building surveyor or authorised person must give written notice of the extension to the builder.