BUILDING ACT 1993 - SECT 56

Decision on application for occupancy permit

    (1)     The relevant building surveyor must decide an application for an occupancy permit under this Division by—

        (a)     issuing the permit; or

        (b)     issuing the permit with conditions; or

        (c)     refusing the permit.

    (2)     The regulations may prescribe a time within which the relevant building surveyor must decide an application for an occupancy permit.

S. 56(3) amended by No. 21/2017 s. 99.

    (3)     The relevant building surveyor is taken to have refused an occupancy permit if the application is not decided within the prescribed time.