(1) The adjoining owner, not later than 14 days after service on the adjoining owner of the notice of proposed building work, must—
S. 85(1)(a) amended by No. 66/2004 s. 9(2).
(a) give to the owner a notice agreeing to the proposed protection work; or
S. 85(1)(b) amended by No. 66/2004 s. 9(2).
(b) give to the owner and the relevant building surveyor a notice—
(i) disagreeing with the proposed protection work; or
(ii) requiring more information to be given to enable the proposal to be considered by the relevant building surveyor.
S. 85(2) amended by No. 21/2017 s. 99.
(2) Subject to sections 90 and 91, an adjoining owner who fails to give a notice under subsection (1) within the required time is taken to have agreed to the proposed protection work.
S. 85(3) inserted by No. 66/2004 s. 9(3).
(3) A notice given under this section must contain the prescribed information.