(1) The chief dispute resolution officer must give a copy of each stop work notice to all parties to the domestic building work dispute.
(2) A stop work notice takes effect on the notice being given to the builder.
(3) The stop work notice ceases to have effect on the issuing of a certificate of conciliation under section 45F in relation to the domestic building work dispute.
(4) If a stop work notice is given in relation to domestic building work, the period during which the notice is in effect is not to be counted in any period within which the domestic building work must be completed under the domestic building contract.