BUILDING REGULATIONS 2018 - REG 39

Building surveyor to provide copy of permit

    (1)     The relevant building surveyor must within
7 days after issuing a building permit give to the applicant for the building permit—

        (a)     a copy of the permit; and

        (b)     2 copies of the plans, specifications and other documents (except for computations or reports) lodged with the application (whether or not with amendments) with evidence of approval stamped and endorsed on them.

    (2)     The relevant building surveyor must give a copy of a building permit within 7 days after the issue of the permit to—

        (a)     the builder named in the permit; and

        (b)     the owner of the allotment to which the permit relates if the owner did not apply for the permit.