BUILDING REGULATIONS 2018 - REG 53

Commencement of work

If a building permit is issued, the building work must commence—

        (a)     in the case of the re-erection of a Class 1 or 10 building, within 6 months of the date of issue of the building permit; or

        (b)     in any other case, within 12 months of the date of issue of the building permit.