(1) Despite regulation 332, Subdivision 2 of Division 2 of Part 5.1 (Construction) applies to a construction project the cost of which is $250 000 or more if the construction contract for the project was entered into before 1 July 2014.
Note
1 July 2014 was the commencement date of the Occupational Health and Safety Amendment Regulations 2014.
(2) An application for registration to perform construction work made but not determined by the Authority under regulation 6.2.15 of the former Regulations immediately before the commencement day is taken, on and from the commencement day, to be an application for a construction induction card under regulation 344 of these Regulations.
(3) A person who was registered to perform construction work under regulation 5.1.21 of the former Regulations immediately before the commencement day is taken, on and from the commencement day, to comply with the requirements of Division 3 of Part 5.1 (Construction) of these Regulations.