(1) For the purposes of section 44(3)(c) of the Act, a certificate of compliance must contain all the details required by the certificate of electrical safety.
(2) Despite subregulation (1), detail as to the maximum demand of the installation at the time of completion of the work in amps per phase need only be completed if the work has increased the maximum demand of the installation.
(3) Despite subregulation (1), detail as to the consumers mains capacity of the installation in amps need only be completed if the work has increased the maximum demand of the installation.