(1) In this section
—
relevant area means the Mitchell Plateau area or
that area modified to the extent necessary to reflect any changes to the
boundaries of land contiguous to that area resulting from survey or cadastral
information.
(2) Despite anything
in the Mining Act 1978 , a tenement application cannot be made during the
designated period in respect of land wholly or partly within the Mitchell
Plateau area.
(3) For the purposes
of subsection (2), the designated period is the period —
(a)
beginning on the day on which the Alumina Refinery (Mitchell Plateau)
Agreement (Termination) Act 2015 section 6 comes into operation; and
(b)
ending on the day fixed under subsection (4).
(4) When the Minister
is satisfied that the relevant area has been reserved under the
Land Administration Act 1997 Part 4 for the purposes of a national park and
classified as a class A reserve under that Part, the Minister must, by notice
published in the Gazette , fix a day for the purposes of subsection (3)(b).
(5) The day fixed must
be the day after the day on which the notice is published in the Gazette .
[Section 5C inserted: No. 31 of 2015 s. 6.]