(1) A permit authority
may make an order (a building order ) in respect of one or more of the
following —
(a)
particular building work;
(b)
particular demolition work;
(c) a
particular building or incidental structure, whether completed before or after
commencement day.
(2) A building order
must be in an approved form and must be directed to any one or more of the
following persons as is appropriate in the case —
(a) if a
building permit is in effect for the particular building work, the person
named as the builder on the permit;
(b) if a
demolition permit is in effect for the particular demolition work, the person
named as the demolition contractor on the permit;
(c) a
person who is an owner of the land on which the particular building or
demolition work is being, or has been, done;
(d) a
person who is an owner or occupier of the land on which the particular
building or incidental structure is located.