BUILDING ACT 2011 - SECT 33

33 .         Notice of completion

        (1)         The responsible person in relation to a permit must, within 7 days of completion of the work, or the stage of the work, for which the permit was granted, give notice of completion to a relevant permit authority.

        Penalty: a fine of $10 000.

        (2)         A notice of completion must —

            (a)         be in an approved form; and

            (b)         state that the work, or the stage of the work, for which the permit was granted, is completed; and

            (c)         be accompanied by a copy of a certificate for each inspection or test mentioned in section 25(3)(h) or (4)(f) that applies to the permit.