CONSTRUCTION CONTRACTS (FORMER PROVISIONS) ACT 2004 - SECT 10

10 .         Prohibited: provisions requiring payment to be made after 42 days

                A provision in a construction contract that purports to require a payment to be made more than 42 days after the payment is claimed is to be read as being amended to require the payment to be made within 42 days after it is claimed.

        [Section 10 amended: No. 55 of 2016 s. 7.]