(1) In the course of
conducting a review under section 128(1), the Coordinator must seek public
comment on the extent to which the State electricity objective has been or is
being met (the issue ).
(2) The Coordinator
must ensure that a notice giving a general description of the issue is —
(a)
published in a daily newspaper circulating throughout the State; and
(b)
posted on a website maintained by the Coordinator.
(3) The notice must
include —
(a) a
statement that any person may, within a specified period, make written
submissions on the issue to the Coordinator; and
(b) the
address (including an email address) to which the submissions may be delivered
or sent.
(4) The period
specified under subsection (3)(a) must not end less than 30 days after the day
on which the notice is published under subsection (2)(a).
(5) The Coordinator
must have regard to any submission made in accordance with the notice.
[Section 129 amended: No. 9 of 2020 s. 23; No. 1
of 2024 s. 35.]