(1) An undertaker or
pipeline licensee aggrieved by a determination of the Director under
section 13J(4) may apply in writing to the Director for a review of the
determination.
(2) The application is
to be made within 14 days after the applicant receives a notification of the
determination or within such further period as the Director in a particular
case allows.
(3) The Director must
give the applicant a reasonable opportunity to make submissions in relation to
the application.
(4) The Director,
after considering submissions (if any) made under subsection (3), may
determine the application by —
(a)
confirming the determination; or
(b)
varying the determination; or
(c)
cancelling the determination and making a new determination under
section 13J(4), which determination is not subject to review under this
section.
(5) The Director must
give the applicant written notice of his or her determination.
[Section 13M inserted: No. 5 of 2007 s. 32.]