(1) In this
regulation —
commencement day means 1 May 2023;
pre‑commencement delivery temperature
requirements means the requirements —
(a) set
out in AS/NZS 3500.4:2018 (Heated water services) clauses 1.11.2 and
1.11.3; and
(b)
applied under Part 6 as in force immediately before commencement day.
(2) The
pre‑commencement delivery temperature requirements apply in relation to
the following plumbing and plumbing work —
(a) a
new heated water installation commenced during the period of 12 months
beginning on commencement day;
(b) a
solar water heater installation, commenced during the period of 12 months
beginning on commencement day, that is replacing or relocating an existing
water heater.
(3) The plumbing
standards that apply on and after commencement day to plumbing and plumbing
work commenced, but not completed, before commencement day are the plumbing
standards as in force at the time the work for the plumbing or plumbing work
was commenced.
[Regulation 112 inserted: SL 2022/163
r. 9