(1) When major
plumbing work is completed, the licensed plumbing contractor or permit holder
responsible for the work must, within 5 working days after the day on
which the work is completed —
(a) give
the Board a certificate of compliance for the work that complies with this
regulation; and
(b) give
a copy of the certificate to —
(i)
if the work relates to building work carried out under a
building permit — the person named as the builder on the building
permit; or
(ii)
otherwise — the owner or occupier of the place
where the work was carried out;
and
(c) give
a copy of the certificate to the local government in whose district the work
was carried out if the work is drainage plumbing work and the drainage
plumbing is not, and is not intended to be, connected to a sewer.
Penalty for this subregulation: a fine of
$5 000.
(2) The certificate
must certify that —
(a) the
plumbing that is the result of the work (the principal plumbing ), and any
other plumbing that the certificate must cover because of
subregulation (5), complies with the plumbing standards; and
(b)
existing plumbing that any of the plumbing referred to in paragraph (a)
relies upon for its safe and effective operation is safe and in proper working
order.
(3) The certificate
must be in the approved form.
(4) The certificate
need not cover existing plumbing to the extent to which, because of
circumstances beyond the control of the licensed plumbing contractor or permit
holder, the contractor or permit holder cannot inspect, test, repair or
replace the existing plumbing.
(5) If —
(a) the
principal plumbing includes or relies upon plumbing that is the result of
plumbing work for which another licensed plumbing contractor or permit holder
(the previous contractor or permit holder ) is responsible; and
(b) the
plumbing work of the previous contractor or permit holder was not completed by
the previous contractor or permit holder; and
(c) a
certificate of compliance for the plumbing work of the previous contractor or
permit holder has not been given; and
(d) the
plumbing of the previous contractor or permit holder is essential to the safe
and effective operation of the principal plumbing,
the certificate must
cover the plumbing of the previous contractor or permit holder.
(6) A licensed
plumbing contractor or permit holder who has given a certificate of compliance
must keep a copy of the certificate at their principal place of business for
at least 6 years after giving the certificate.
Penalty for this subregulation: a fine of
$3 000.
[Regulation 42 inserted: Gazette
28 Jun 2004 p. 2417‑18; amended: Gazette
7 Oct 2005 p. 4521; 29 Apr 2016 p. 1344;
SL 2024/12 r. 21.]