Home
| Databases
| WorldLII
| Search
| Feedback
Supreme Court of New South Wales - Court of Appeal |
Last Updated: 29 March 2019
|
Court of Appeal Supreme Court New South Wales
|
Case Name:
|
Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
4 March 2019
|
Decision Date:
|
29 March 2019
|
Before:
|
Bell P at [1];
White JA at [83]; Sackville AJA at [98] |
Decision:
|
1. Leave to appeal granted.
2. Direct that the appellant file the draft notice of appeal within seven days. 3. Appeal dismissed with costs. 4. Order that the $340,000 paid into Court by Grandview be paid out to Budget. |
Catchwords:
|
BUILDING AND CONSTRUCTION – statutory debt under s 14 of Building and
Construction Industry Security of Payment Act 1999 (Cth)
–
creditor’s statutory demand – suspension of work pending payment of
demand – application to set aside statutory
demand under s 459G of
Corporations Act 2001 (Cth) – whether debtor had offsetting claim within
meaning of s 459H
CONTRACTS – purported termination – whether purported termination precluded by election to affirm contract CORPORATIONS – creditor’s statutory demand – application to set aside statutory demand under s 459G of Corporations Act 2001 (Cth) – offsetting claim arising after filing of setting-aside application – Graywinter principle – offsetting claim foreshadowed by s 459G affidavit – whether offsetting claim “genuine” PRACTICE AND PROCEDURE – funds paid into Court – discretion in relation to release of funds |
Legislation Cited:
|
Building and Construction Industry Security of Payment Act 1999 (NSW), ss
14, 15, 27
Corporations Act 2001 (Cth), ss 459H, 459J Federal Court (Corporations) Rules 2000 (Cth) Federal Court Rules 1979 (Cth), r 36B |
Cases Cited:
|
Australian Beverage Distributors Pty Ltd v Cranswick Premium Wines Pty Ltd
[2004] NSWSC 877; 50 ACSR 544
Britten-Norman Pty Ltd v Analysis & Technology Australia Pty Ltd (2013) 85 NSWLR 601; [2013] NSWCA 344 Creata (Aust) Pty Ltd v Faull [2017] NSWCA 300; (2017) 125 ACSR 212 Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd [2014] WASCA 91 Douglas Aerospace Pty Ltd [2015] NSWSC 167 Equuscorp Pty Ltd v Perpetual Trustees WA Ltd (1997) 80 FCR 296; [1997] FCA 1366; 25 ACSR 675 Eyota Pty Ltd v Hanave Pty Ltd (1994) 12 ACSR 785 Financial Solutions Australasia Pty Ltd v Predella Pty Ltd (2002) 26 WAR 306; [2002] WASCA 51 Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd (No 2) [2018] NSWCA 341 Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd [2018] NSWSC 1647 Graywinter Properties Pty Ltd v Gas & Fuel Corporation Superannuation Fund (1996) 70 FCR 452; [1996] FCA 822 Hopetoun Kembla Investments Pty Ltd v JPR Legal Pty Ltd [2011] NSWSC 1343; 286 ALR 768 In the matter of Citadel Financial Corporation Pty Ltd [2019] NSWSC 65 In the matter of Oztec Pty Ltd [2012] NSWSC 1234 Independent Portable Buildings Pty Ltd v Modular Building Systems Pty Ltd [2011] FCA 511 Infratel Networks Pty Ltd Pty Ltd v Gundry’s Telco & Rigging Pty Ltd [2012] NSWCA 365; 297 ALR 372 Jem Developments Pty Ltd v Hansen Yuncken Pty Ltd [2006] NSWSC 1378; 60 ACSR 393 JKB Holdings Pty Ltd v de la Vega [2013] NSWSC 501 Motor Oil Hellas (Corinth) Refineries SA v Shipping Corp of India (The Kanchenjunga) [1990] 1 Lloyd’s Rep 391 Ozone Manufacturing Pty Ltd v Deputy Commissioner of Taxation (2006) 94 SASR 269; [2006] SASC 91 Pravenkav Group Pty Ltd v Diploma Construction (WA) Pty Ltd (No 3) (2014) 46 WAR 483; [2014] WASCA 132 Re J Group Constructions Pty Ltd [2015] NSWSC 1607; 303 FLR 139 Sargent v ASL Developments Ltd (1974) 131 CLR 634; [1974] HCA 40 Scanhill Pty Ltd v Century 21 Australasia Pty Ltd [1993] FCA 618; (1993) 47 FCR 451 Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq) [2019] NSWCA 11 Spacorp Australia Pty Ltd v Myer Stores Ltd [2001] VSCA 89; 19 ACLC 1270 Thomson v Golden Destiny Investments Pty Ltd (No 2) [2015] NSWSC 1929 TR Administration Pty Ltd v Frank Marchetti & Sons Pty Ltd [2008] VSCA 70; 66 ACSR 67 Tropical Traders Ltd v Goonan (1964) 111 CLR 41; [1964] HCA 20 Wendt v Bruce (1931) 45 CLR 245; [1931] HCA 9 |
Category:
|
Principal judgment
|
Parties:
|
Grandview Ausbuilder Pty Ltd (Applicant/Appellant)
Budget Demolitions Pty Ltd (Respondent) |
Representation:
|
Counsel:
V Culkoff (Applicant/Appellant) M Pesman SC, N Allan (Respondent) Solicitors: Julie A Orsini (Applicant/Appellant) Ziman & Ziman (Respondent) |
File Number(s):
|
2018/346856
|
Decision under appeal:
|
|
Court or Tribunal:
|
Supreme Court
|
Jurisdiction:
|
Equity
|
Citation:
|
Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd [2018] NSWSC
1647
Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd (No 2) [2018] NSWSC 1713 |
Date of Decision:
|
2 November 2018
7 November 2018 |
Before:
|
Parker J
|
File Number(s):
|
2018/56438
|
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11)
that unless the Court otherwise orders, a judgment or order is taken to be
entered when it is recorded in the Court's computerised
court record system.
Setting aside and variation of judgments or orders is dealt with by Rules 36.15,
36.16, 36.17 and 36.18. Parties should in particular note the time limit of
fourteen days in Rule 36.16.]
JUDGMENT
Introduction
“a genuine claim that the company has against the respondent by way of counterclaim, set-off or cross-demand (even if it does not arise out of the same transaction or circumstances as a debt to which the demand relates)”.
”Grandview undertake to commence proceedings as quickly as reasonably practicable to assert its offsetting claim (along with any other claim arising out of the subcontract), to pay the sum of $220,000 into Court in those proceedings, and thereafter to prosecute the proceedings with all due dispatch”.
In the event, Grandview proffered no such undertaking with the consequence that, given the conclusions reached in respect of the other two alleged Offsetting Claims, the application to set aside the statutory demand was dismissed with costs.
Relevant Background
“Due to the festive holiday season celebration, our site in Villawood (Maple Village) will be closed from Friday 22 Dec 2017 to 04 Feb 2018.
Site work will resum[e] on Monday 05 February 2018.
From all of the team at Grandview, we look forward to continue working with you throughout 2018.
Wishing you all a wonderful Christmas and a safe and prosperous New Year.” (Emphasis added)
“representatives of Grandview contacted representatives of Budget on the site and told them to stop work or the police would be called. Eventually Budget completed work on that day but did not return to the site thereafter.”
“In reference to the payment claim dated 21 November 2017 regarding the amount of $498,528.10 inclusive of GST.
We have not received full payment of the scheduled amount as per your payment schedule dated 1 December 2017.
This is formal notice of my intent to suspend work and supply of related goods and services under section 27 of the Building and Construction Industry Security of Payment Act 1999 (NSW). The period of suspension begins two business days after receipt of this notice unless payment has been received.
Please be aware of the following:
• Suspension of work and supply of related goods and services can continue under the act until the end of the period of three (3) business days immediately following the date we receive payment.
• In exercising our right to suspend work and supply of related goods and services, on the occurrence of any loss due to suspension, you become liable to pay the amount of loss or expense.
• In exercising our right to suspend work and supply of related goods and services, we are not liable for any loss or damage suffered by you during this period of suspension.”
“(1) A claimant may suspend the carrying out of construction work (or the supply of related goods and services) under a construction contract if at least 2 business days have passed since the claimant has caused notice of intention to do so to be given to the respondent under section 15, 16 or 24.
(2) The right conferred by subsection (1) exists until the end of the period of 3 business days immediately following the date on which the claimant receives payment for the amount that is payable by the respondent under section 15 (1), 16 (1) or 23 (2).
(2A) ...
(3) A claimant who suspends construction work (or the supply of related goods and services) in accordance with the right conferred by subsection (1) is not liable for any loss or damage suffered by the respondent, or by any person claiming through the respondent, as a consequence of the claimant not carrying out that work (or not supplying those goods and services) during the period of suspension.”
“(1) This section applies if the respondent:
(a) becomes liable to pay the claimed amount to the claimant under section 14 (4) as a consequence of having failed to provide a payment schedule to the claimant within the time allowed by that section, and
(b) fails to pay the whole or any part of the claimed amount on or before the due date for the progress payment to which the payment claim relates.
(2) In those circumstances, the claimant:
(a) may:
(i) recover the unpaid portion of the claimed amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or
(ii) make an adjudication application under section 17 (1) (b) in relation to the payment claim, and
(b) may serve notice on the respondent of the claimant’s intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.
(3) A notice referred to in subsection (2) (b) must state that it is made under this Act.
(4) If the claimant commences proceedings under subsection (2) (a) (i) to recover the unpaid portion of the claimed amount from the respondent as a debt:
(a) judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1), and
(b) the respondent is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract.”
“Dear Frank;
While clearly this email doesn’t explain the reasons behind the suspension of works, and keeping in mind our large excavators and other sources remain on site,
The continuous failed attempts to contact Jason directly, putting our company in huge risk financially and future business opportunity, and we maintain the wright [sic] of claiming compensation to loss and damage,
Your efforts of passing our concern to your management highly appreciated. Looking forward for [sic] an urgent meeting ASAP to discuss the issue.”
“i am in china, there is time differents [sic] and maybe Some technical issue, My australian number doesn’t working [sic] properly in china.
We are still working on s96 and new DA, According to council, it might take more than three months.
I am aware you have one Claim overdue. but we have some issues on that claim, I need to discuss with peter, when I back to sydney.
Do not waste money on your lawyer, we can fighting [sic] on the court for a year, get same result. let’s sit down talk about how to pay you. That will save you a lot of legal fee.
Try to call me after Lunch time, Don’t too earlier, There is time difference between china and australia.”
“23. Budget’s failure to meet the milestone dates for the works and the resulting delays occasioned to the works have caused Grandview to suffer loss.
24. Pursuant to clause 30 and item 15 of the agreement, Budget is liable to Grandview for liquidated damages of $4,000.00 plus GST per day in respect of each milestone completion date which Budget has failed to meet, such damages being separate and distinct from each other and not cumulative.
25. Annexed and marked “E” is a schedule prepared by Grandview’s site team which identifies the works which were required to be performed by Budget and their corresponding milestone dates. It further identifies the actual dates upon which Budget completed those works and provides a calculation of the liquidated damages which are due to Grandview by reason of Budgets failure to meet those milestone dates.
26. Further, Budget has failed to meet the bulk excavations completion date of 12 December 2017. That, along with other work remains incomplete. Liquidated damages are continuing to accrue each day in respect of the works that remain incomplete, at the rate of $4,000.00 plus GST and as set out in annexure E.
27. On 21 January 2018, Grandview received a further payment claim from Budget purporting to claim delay costs by reason of the site being closed for the vacation period. Grandview responded to that claim by way of service of a payment schedule. Annexed and marked “F” a copy of that claim and the payment schedule as it relates to that claim.
28. Budget has not returned to the site since the Christmas period and accordingly its works remain incomplete.
29. Budget’s failure to complete the work in accordance with the program has left Grandview with no option but to exercise its rights under the agreement to terminate the agreement and engage another contractor to finish the works. This is likely to cause Grandview to incur additional costs which will be claimed against Budget.
30. By reason of the matters set out above, Grandview has a defence, crossclaim and setoff against Budget which exceeds the amount claimed to be due to it on an interim basis and as set out by Budget in the Statutory Demand.”
“On 2 March 2018, Grandview served on you a Notice to Show Cause in accordance with clause 40 of the general conditions of the Subcontract Agreement entered into 19 June 2017 (“the subcontract”).
You failed to show reasonable cause or to provide a written response to the Notice, as required by the Notice, or at all.
Further, on 13 and 17 March 2018 you attended the site and removed materials and equipment intended to be used to complete the subcontract works, thereby prejudicing Grandview’s right to, in mitigation of further delay and damage, take out your hands and engage another party to complete the subcontract works.
Given your failure to show reasonable cause and given your conduct referred to above, Grandview has no option but to terminate the subcontract pursuant to clause 40(e)(ii).
Grandview hereby gives you notice that, pursuant to subclause 40e(ii), the subcontract is now terminated.
Grandview has now engaged an expert to assess the work performed by you and which is required to be completed pursuant to the terms of the subcontract.
Pursuant to its contractual rights, Grandview gives you notice that, in addition to its claim for liquidated damages, Grandview will deduct from any money that may have been paid to you and/or may be due to you due, all damages resulting from the termination, including but not limited to, the cost of any Expert together with any rectification costs, and the difference between the sum allowed to you and the cost to complete the work, given the subcontract price.”
“We refer to the contract between our respective clients who are referred to above.
Your client has clearly, by its actions, evinced its intention not to be bound by the terms of the contract and has thereby repudiated the contract. Our client accepts that repudiation and has elected to consider the contract as terminated.
Our client will in due course and in the event that your client is able to overcome the matter presently before the Supreme Court relating to its solvency, claim from your client such damages as it might be entitled to consequent upon your client’s wrongful actions.”
The Milestone Damages Claim
“Liquidated milestone damages
[26] As propounded by counsel, this offsetting claim was based on cl 30(a)(ii). Mr Zhang’s affidavit stated:
Further, Budget has failed to meet the bulk excavations completion date of 12 December 2017. That, along with other work remains incomplete. Liquidated damages are continuing to accrue each day in respect of each of the works that remain incomplete, at the rate of $4,000.00 plus GST...
[27] Mr Zhang annexed to the affidavit a schedule prepared by “Grandview’s site team” which calculated liquidated damages by reference to works which were required to be performed, corresponding milestone dates and what was said to be actual completion dates. The total amount was $3.816 million.
[28] This is a startling figure in the context of a contract which provided for a total contract work price of $2.5 million and where, as will be seen below, Grandview’s own expert put the value of work left to do at $1.1 million. But there is a more fundamental problem than this. Item 15(b), which was to prescribe the rate per day for failure to reach milestones for the purposes of cl 30(a)(ii), was left blank. The Sub-Contract thus did not, in its terms, justify the claim.
[29] When this was pointed out to counsel for Grandview, he asserted that it was a mistake and that Grandview would require the contract to be rectified. But this is not satisfactory. Mr Zhang’s affidavit contained not one word about rectification; indeed, so far as I can see, it had never been mentioned until counsel put it forward, apparently on the spur of the moment, at the hearing. The principle, known as the “Graywinter principle” from Graywinter Properties Pty Ltd v Gas & Fuel Corp Superannuation Fund (1996) 70 FCR 452; [1996] FCA 822, that it is not open to a plaintiff applying to set aside a statutory demand to introduce at the hearing a new ground not supported by the affidavit filed in support of the applications, is well established. This alleged offsetting claim fails in its entirety.”
15. The amount of Liquidated and Ascertained Damages
(Clause 30(a))
|
$ 4000
|
+GST Per day
|
15(a) the Rate per day for the whole of the Works (Clause
30(a)(i))
|
$ 4000
|
+GST Per day
|
15(b) the Rate per day for Milestone
(clause 30(b))
|
|
|
Milestone 1
|
$
|
+GST Per day
|
*The rates for each are separate and distinct from each other and are
not cumulative.”
|
|
|
“a. If the Subcontractor fails to achieve Completion of the whole of the Subcontract Works by the Date of Practical Completion and or a Milestone by the Milestone Completion Date (as the case may be) the Subcontractor will be liable to pay the Builder liquidated damages as a debt due and owing at the following rates:
i. In the case of the whole of the Subcontract Works at the rate stated Item 15(a) of Annexure A.
ii. In the case of the Subcontract Works the subject of a Milestone at the rate(s) stated in Item 15(b) of Annexure A for each Milestone as specified in Item 12 of Annexure A to an aggregated maximum total of not more than the rate stated in Item 15(a) of Annexure A for every day after the Contractual Completion Date to and including the Actual Completion Date.
If however the Contract is terminated under clauses 40 or 42 before the Subcontract reaches Practical Completion, any applicable liquidated damages for failure to achieve Completion by the Contractual Completion date will run to the date of termination of the Contract.
b. The Builder in its discretion, may demand and deduct payment of the liquidated damages amount from any amount otherwise payable to, or security provided by the Subcontractor, including any retention monies then held by the Builder. A failure by the Builder at any time to demand payment or to deduct withhold or set off the liquidated damages will not amount to a waiver of or otherwise affect the Builder’s rights and entitlements.” (Emphasis added)
“Milestone 1 As per the attached construction programme
Description of Milestone Completion date shall not exceed12/12/1612/12/17
Milestone 1 Completion Date”
“Milestone(s) means a programmed event(s) signifying the completion of a major activity or a set of related activities which form part of the Subcontract Works and which are referred to in Item 12 and/or set out in the Subcontract Program as annexed (as applicable).”
The Loss of Bargain Damages Claim
“[n]o, it’s just been overcharged. It is just there is a contract price of $2.3 million odd. 2.2 has been charged. 1.1 has been paid. So there is a claim for 1.1 and there is yet $1.1 million odd worth of work to be completed. So we say we have been overcharged to this point by about a million.”
“[w]hat I am just sort of trying to work out is, are we in the territory of you actually contesting something that was the subject matter of a progress claim, that you could have raised and is that relevant to whether this is a genuine claim?”
to which counsel gave the candid response “[t]here is that, your Honour”, accepting that such a challenge was foreclosed on the authority of Douglas and Diploma (see [5] above).
“[50] Mr Zhang’s affidavit did not contain any calculation of the amount claimed under this head. In Mr Brincat’s report which was dated 28 April, he assessed the cost of work to be completed at approximately $1.1 million
[51] Counsel for Budget attacked this figure. He submitted that it contained, on its face, arithmetical errors resulting from Mr Brincat having multiplied where he should have divided and the like. Counsel contended that, even accepting everything else Mr Brincat said, the figure was only approximately $425,000. Budget’s expert, Mr Sanig, assessed the cost of completing the work at approximately $260,000. But in my view there is a more fundamental objection.
[52] Grandview’s entitlement under the contract was to have the contract works completed by Budget at the agreed contractual price. The cost to completion as it now stands, having regard to the work done by Grandview, is not an item which of itself can be claimed under the contract. It is only one of the integers in the calculation of Grandview’s loss of bargain damages.
[53] If Grandview has validly terminated the contract, it will be entitled to damages which would put it in the position in which it would be had the contract been completed in accordance with its terms. The first integer in this calculation will be the amount required to complete the works to the contractual standard. But it is necessary to take account of what Grandview would have had to pay under the subcontract. Using Mr Brincat’s figures, one adds the cost of completion of the works ($1.1 million) to the amount already paid ($1.2 million). But to complete the process, it is necessary to subtract the contract price. This is given by Mr Brincat, including variations assessed, as $2.5 million. On these figures, the figure for loss of bargain damages is negative and nothing is recoverable.
[54] This is consistent with common sense. The amount claimed by Budget is of the same order in magnitude as the amount assessed by Mr Brincat to complete the works. If Grandview paid the amounts demanded, it would be open to it to make a “true” restitution claim for defective work. If Grandview does not pay, then it cannot, consistently with the SOP Act, make an offsetting claim for that work. To conclude otherwise would be to allow Grandview to evade the decision in Douglas and the decision in Diploma on which it was based. This alleged offsetting claim fails in its entirety.”
“In addition to the reasons his Honour gave for declining to set aside the statutory demand, his Honour should also have found that the Applicant had no offsetting claim for loss of bargain damages because it had no entitlement to terminate the contract between the applicant and the respondent a at 9 April 2018, or any other date after 20 December 2017.”
“It is likely then that, had it been necessary for Parker J to decide upon the genuineness of Grandview’s claims, the times at which they arose, and the value they might truly have contained, his Honour would have concluded the claim was cynical, too late and for too little.... Grandview’s purported termination, after proceedings commenced, was an unconvincing attempt to create an offsetting claim for the resultant loss of the bargain.”
“[46] The meaning of the expression “offsetting claim”, like the meaning of "genuine dispute" has been illuminated by analogies found in applications for injunctions to restrain the commencement, advertisement and prosecution of winding-up proceedings pre-dating the enactment of s 459G and in the opposing of a notional application by the person who has served the statutory demand for summary judgment against the company for the debt the subject of the demand: Chase Manhattan at 136. Thus, when deciding whether an offsetting claim exists, the test is whether the court is satisfied that there is a serious question to be tried that the person on whom the demand has been served has an offsetting claim: Scanhill Pty Ltd v Century 21 Australasia Pty Ltd [1993] FCA 618; (1993) 12 ACSR 341 at 357, or that the claim is not frivolous or vexatious: Chadwick Industries (South Coast) Pty Ltd v Condensing Vaporisers Pty Ltd (1994) 13 ACSR 37, or that it is not fictitious or merely colourable: Edge Technology Pty Ltd v Lite-on Technology Corporation [2000] NSWSC 471; (2000) 156 FLR 181 at 184-5, citing Jesseron Holdings Pty Ltd v Middle East Trading Consultants Pty Ltd (No 2) (1994) 13 ACSR 787.
[47] The test whether an offsetting claim exists is the same as for a genuine dispute, that is to say, the claim must be bona fide and truly exist in fact and that the grounds for alleging the existence of the dispute are real and not spurious, hypothetical, illusory or misconceived. The issue is whether the offsetting claim is bona fide, real and not spurious: Edge Technology per Santow J at [25].
[48] I do not think that the test identified by Santow J imposes a more onerous task on the party disputing the statutory demand than the serious question test. The expression "good faith" means arguable on the basis of facts asserted with a sufficient particularity to enable the court to determine that the claim is not fanciful: Macleay Nominees Pty Ltd v Belle Property East Pty Ltd [2001] NSWSC 743 per Palmer J. McPherson JA expressed the same concept in these terms in JJMMR Pty Ltd v LG International Corporation [2003] QCA 519 at [18]:
Anyone can make a claim to a right of setoff against a creditor. What the definition in s 459H(5) requires, however, is that it be "genuine". The same word in s 459H(1) has already elicited so many synonyms and shades of meaning that it will not help to add more. Its antithesis is to be seen in the word "artificial". The claim to set off against the debt demanded must not have been manufactured or got up simply for the purpose of defeating the demand made against the company. It must have an existence that is objectively demonstrable independently of the exigencies of the demand that evoked it.
The observations of Palmer J and McPherson JA were applied by Chesterman J in Cooloola Dairies Pty Ltd v National Foods Milk Ltd [2004] QSC 308; [2005] 1 Qd R 12.”
“This does not mean that the court must accept uncritically as giving rise to a genuine dispute, every statement in an affidavit “however equivocal, lacking in precision, inconsistent with undisputed contemporary documents or other statements by the same deponent, or inherently improbable in itself, it may be” not having “sufficient prima facie plausibility to merit further investigation as to [its] truth. (cf Eng Mee Yong v Letchunanan [1980] AC 331 at 341), or “a patently feeble legal argument or an assertion of facts unsupported by evidence”: cf South Australia v Wall (1980) 24 SASR 189 at 194.”
“In judging the sufficiency of the evidence to give rise to an offsetting claim, the question is not whether the evidence is sufficient to establish the offsetting claim or its amount, but whether it is sufficient to establish that the offsetting claim is genuine and its genuine level (Re Morris Catering (Australia) Pty Ltd (1993) 11 ACSR 601 at 605; Britten-Norman Pty Ltd v Analysis and Technology Australia Pty Ltd (2013) 85 NSWLR 601; [2013] NSWCA 344 at [48] and [49]). It is sufficient if there be a plausible contention requiring investigation (Britten-Norman Pty Ltd v Analysis and Technology Australia Pty Ltd at [70]). The offsetting claim should have a sufficient objective existence and prima facie plausibility to distinguish it from a merely spurious claim, bluster or assertion and not be merely fanciful or futile (TR Administration Pty Ltd v Frank Marchetti & Sons Pty Ltd [2008] VSCA 70; (2008) 66 ACSR 67 at [71] cited with approval in Britten-Norman Pty Ltd v Analysis and Technology Australia Pty Ltd at [52]-[53]).”
“The Builder may deduct from moneys due to the Subcontractor any money due from the Subcontractor to the Builder and if those moneys are insufficient, the Builder may have recourse to retention monies under Clause 5 of this Subcontract and, if they are insufficient, to any security under this Subcontract and any balance owing shall be a debt due and payable to the Builder and may be adjusted against any payment drawn including moneys owed on another Subcontract related to a different Project for the Builder.”
“The Builder may deduct from monies due or claimed to be due to the Subcontractor any money due or claimed to be due from the Subcontractor (whether on account of a breach of contract, delay costs or otherwise) to the Builder and if those monies are insufficient, the Builder may at his election have recourse to any security under this Subcontract.”
Conclusion
“a payment into Court will not necessarily give Budget any priority interest, nor would it constitute Budget a secured creditor. If, during the course of the court proceedings, Grandview is wound up, the liquidator would undoubtedly have access to the monies paid into Court for the purposes of the winding up, including for distribution amongst the creditors generally. If Grandview is wound up after the monies are paid out to Budget, the monies would fall to be dealt with in accordance with the Corporations Act, Pt 5.6.”
“23. Budget’s failure to meet the milestone dates for the works and the resulting delays occasioned to the works have caused Grandview to suffer loss.
24. Pursuant to clause 30 and item 15 of the agreement, Budget is liable to Grandview for liquidated damages of $4,000.00 plus GST per day in respect of each milestone completion date which Budget has failed to meet, such damages being separate and distinct from each other and not cumulative.
25. Annexed and marked ‘E’ is a schedule prepared by Grandview’s site team which identifies the works which were required to be performed by Budget and their corresponding milestone dates. It further identifies the actual dates upon which Budget completed those works and provides a calculation of the liquidated damages which are due to Grandview by reason of Budget[‘]s failure to meet those milestone dates.”
“I have addressed to this point the aspect of the ‘genuine dispute’ concept that concentrates on a showing of serious question to be tried or plausible contention requiring further investigation. Another aspect, no less important, requires that the serious question or plausible contention not be something merely created or constructed in response to the pressure represented by the service of the statutory demand. [The issue was framed in that way in Ligon 158 Pty Ltd v Huber [2016] NSWCA 330; 117 ACSR 495 at [10] and [13].] If the dispute is of that quality and is accordingly not advanced in good faith, it is not ‘genuine’.”
“at least in most cases, it is not expected that the court will embark upon any extended inquiry in order to determine whether there is a genuine dispute between the parties and certainly will not attempt to weigh the merits of that dispute. All that the legislation requires is that the court conclude that there is a dispute and that it is a genuine dispute”.
**********
[1] [1994] VicRp 61; [1994] 2 VR
290.
[2] Mibor
Investments Pty Ltd v Commonwealth Bank of Australia at
295.
[3] [1997] FCA 1366; (1997)
25 ACSR 675 at 696 per curiam.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWCA/2019/60.html